Penny Green Street Reconstruction Project

map of street reconstruction in Penny Green subdivision

Current Status

Utility relocation work by WaterOne, Kansas Gas, and a few communication companies is scheduled until May 2024. The City’s portion of the project is in the final design stages and is scheduled to begin in June.

Roadway Cross-Section Diagram (PDF)

Aerial Map (PDF)

Schedule and Phasing Map (PDF)

Project Description

The Penny Green Subdivision Street Reconstruction Project will completely reconstruct 85% of the subdivision. The road is past its useful life, and typical preventative maintenance strategies, such as mill and overlays, are no longer cost-effective due to how quickly these strategies fail.

This project will consist of several utility modifications and upgrades.  This utility work will not be completed by the City or its contractor. The City and its contractor will then complete removal of the roadway, subgrade modifications, spot replacement of sidewalk and curb and gutter, streetlight upgrades and new asphalt pavement.


Project Phasing

The phasing plan below is for the street reconstruction portion of the City’s project. This is the portion where the roadway is being completely removed and new base and asphalt material are being placed. 

During this process, there may be sporadic concrete work and street lighting work occurring in other areas of the projects. Additionally, the utility work is scheduled from March to May will not follow this phasing plan. 

Schedule and Phasing Map (PDF)

Cost and Funding Sources

Total cost: $4 million

Funding sources: Capital Improvement Fund – Pavement Reconstruction Program. See the 2024–2028 Capital Improvement Program for details.


Timeline

Utility modifications: March to June 2024

Final design: March 2024

Bid opening: April 2024

City construction starts: June 2024

Project Team

Engineering Design and Inspection: Olsson Associates

Construction Contractor: Not selected

Reasons for Complete Reconstruction

The City and its consultant have reviewed the asphalt and underlying base material (subgrade) on all the streets throughout the Penny Green Subdivision. The team found that the subgrade soils mostly consist of a well-compacted fill made of clay and sand with spot locations of overly saturated clay. This leads to some spot failures but is not the main reason for issues along the roadway. The apparent issue is more closely related to the asphalt pavement and base material that consists of a reclaimed aggregate base and a thin layer of asphalt. This thin layer of asphalt has not held up well over time. 

The best long-term strategy is to completely replace the roadway. This includes removing unsuitable soil, densifying the subgrade, installing an aggregate base, and finally installing the base and surface asphalt. 

Frequently Asked Questions

None at this time.

Have questions?

Contact Project Manager Cody Wilbers at [email protected] or 913.477.7660.